run-tests: add more scheduling weight hints

The scheduler would like to order test execution by expected run-time,
but doesn't know much about how long a test will run. It thus uses
test size as a proxy for run-time. By tweaking these weights we can
keep CPUs more evenly busy and thus finish sooner.

In particular, this change pushes the three currently longest-running
tests closer to the beginning:

test-largefiles-update.t
test-run-tests.t
test-gendoc.t

As the largefiles test is currently the long pole of the test suite
with higher -j factors, the sooner it's started, the sooner the tests
can end.

We also up the weight on some shorter but long-running tests that
could have previously delayed completion with low -j factors by
running very close to the end.
parent a40b623e
No related branches found
No related tags found
No related merge requests found
Loading
0% Loading or .
You are about to add 0 people to the discussion. Proceed with caution.
Finish editing this message first!
Please register or to comment